Scope, source, and method.
Which sheets were read, how many line items came out, what was deliberately left out, and the fact that nothing here is priced.
We took a published municipal drawing set, read the electrical scope sheet by sheet, and produced the schedule you can download below. Every line carries a CSI MasterFormat code, a quantity, a unit, and the sheet it came from.
Circuits from the E-9 circuit schedule, panel equipment from the E-6 layout, the pump terminal panel items from the E-4 item schedule, and major equipment from the E-2 one-line diagram.
Transcribed from E-9 with the conduit trade size for each run, then totalled by gauge and size. Nothing was typed by hand into the summary.
Linear raceway lengths, submittal counts, and two places where the plan and the wiring diagram disagree. Those are marked VERIFY on their own sheet so you can see exactly where a human still has to look.
Download the full workbook. It is the real file, not a preview — five sheets, formatted for Excel.
This is the format your takeoff arrives in: a code, a description you can order against, a quantity, a unit, the sheet it came from, and its status.
| Item | CSI code | Description | Qty | Unit | Sheet | Status |
|---|---|---|---|---|---|---|
| 23 | 26 05 33 00 | Utility transformer, 75 KVA, 240/120V, 3 phase, 4 wire | 1 | EA | E-2, E-3 | Scheduled |
| 27 | 26 24 16 00 | Master control panel (MCP), NEMA 3R(X) stainless steel, 72 x 60 x 24 inch | 1 | EA | E-6 | Scheduled |
| 33 | 26 24 16 00 | Master control panel, power circuit breaker | 3 | EA | E-6 | Scheduled |
| 36 | 26 24 16 00 | Master control panel, solid state soft starter with Profinet module and keypad | 2 | EA | E-4, E-6 | Scheduled |
| 53 | 26 24 16 00 | Master control panel, wireway, horizontal and vertical runs | 6 | EA | E-6 | Scheduled |
| 54 | 26 24 16 00 | Pump terminal panel (PTP), NEMA 4 enclosure 24 x 24 x 10 inch | 1 | EA | E-4 item 1 | Scheduled |
| 60 | 26 32 13 00 | Engine generator, 30 kW diesel standby, 120/240V, 3 phase, with sub-base fuel tank | 1 | EA | E-2 | Scheduled |
| 63 | 11 53 13 00 | Submersible wastewater pump, 7.2 HP | 2 | EA | E-2, E-4 | Scheduled |
| 10 | 26 05 43 00 | Conduit, rigid steel, 2 inch | 2 | LF | E-9, E-3 | Verify |
| 19 | 26 05 26 00 | Ground rod, copperweld, 3/4 inch x 10 foot | 2 | EA | E-2, E-8 | Verify |
| 34 | 26 24 16 00 | Master control panel, distribution circuit breakers | 1 | LS | E-6 | Verify |
| 65 | 26 60 00 00 | Float switch, high level | 3 | EA | E-4 | Verify |
Scheduled means the drawings state the quantity. Verify means they do not, and we said so instead of inventing a number.
Get all 80 linesA quantity schedule you cannot audit is worth very little. The workbook is built so you can walk back to the drawing for every number in it.
Which sheets were read, how many line items came out, what was deliberately left out, and the fact that nothing here is priced.
Eighty lines with CSI code, description, quantity, unit, source sheet, status, and notes. Filterable, sortable, and ready to carry into an estimate.
Each circuit with its from and to, every individual conductor callout, and the conduit trade size for the run.
Twenty-four conductors counted by gauge and type, and ten conduit runs across four trade sizes — derived from the circuit schedule above it.
Every line we could not settle from the drawings alone, with the reason. This is the sheet that makes the rest of it trustworthy.
Upload your PDF or DWG and you get the same structure, scoped to your trade, with the same flagging discipline.
We did not invent a project for the demo. This is a published municipal bid set, and the drawings are linked below so you can check our work against them.
Read the drawing set yourself and check us against it. Open the published bid set PDF — it is a large file, so the schedule is the fastest place to start.
How we count, in detailSame structure, same CSI codes, same flagging discipline — scoped to the trade you are bidding and the plans you actually have.